Examcollection 1z0-1057 Questions are updated and all 1z0-1057 answers are verified by experts. Once you have completely prepared with our 1z0-1057 exam prep kits you will be ready for the real 1z0-1057 exam without a problem. We have Up to date Oracle 1z0-1057 dumps study guide. PASSED 1z0-1057 First attempt! Here What I Did.
Online 1z0-1057 free questions and answers of New Version:
NEW QUESTION 1
You configure one OTBI using Project Cross Subject Area Analysis Real Time. You notice that all measures (Budget, Forecast, Cost, Commitments, Revenue, and Invoice) are not available for Bill-To-Customer and Contract and Contract Line dimensions. Identify the reason for this behavior. (Choose the best answer.)
Answer: D
Explanation:
Ref:https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/faopm/subjectareas.html#Projects_ Analyze real-time information on project performance, including budgets, forecasts, costs, commitments,
revenue, and invoices.
This subject area analysis allows cross subject area analysis between Funding, Invoices, Revenue, Budget, forecasts, Costs areas.
NEW QUESTION 2
Your business user has created a purchase order (PO) that has the following attributes: Accrue at Receipt = Yes
Matching Option = 2 way Receipt Close Tolerance = 100%
After approval, the PO is closed for receiving without creating a receipt. An AP invoice is created by matching to the PO. The user now runs Create Accounting for Receiving Transactions and then the “Import and Process Cost transactions” ESS (Enterprise Scheduler Service) job using the Transaction Source parameter as “Oracle Payables”. The user notices that there is no cost transferred to the projects. Identify two reasons for this problem. (Choose two.)
Answer: BC
NEW QUESTION 3
Which three are part of using the Rapid Implementation for Project Financial Management Applications macro-enabled Microsoft Excel spreadsheet to enter setup data?
Answer: ACD
Explanation:
https://docs.oracle.com/applications/farel12/projectop_gs/OAPFM/OAPFM2264569.htm#OAPFM2159921 Configuring Rapid Implementation: Procedure
Project application administrators can use the rapid implementation feature to set up the Project Financial Management offering. Use the Rapid Implementation for Project Financial Management Applications macro-enabled Microsoft Excel spreadsheet to enter setup data and generate the ProjectsWorkbook.zip. Upload this .zip file to the Setup and Maintenance work area. When the upload completes, the offering is configured based on the setup information that you provide.
Perform the following steps to configure rapid implementation for the Project Financial Management offering:
Prepare setup data.
Generate CSV files.
Upload setup data.
Correct errors, if any, and reload the data.
NEW QUESTION 4
Your client uses Resource Breakdown Structures (RBS) and Resource Mapping to associate amounts to resources. After making some changes to the resources at project level, forecasts are regenerated. After reviewing the cost amounts associated with the resources, you suspect that the cost association does not match your client's expectations. Identify two valid rules based on which cost association works. (Choose two.)
Answer: CD
Explanation:
Reference https://docs.oracle.com/cd/E37583_01/doc.1116/e22598/F458900AN13D82.htm
How Resource Mapping Is Calculated
You can track the cost impact of every resource that has been assigned to a project task and use the resource breakdown structure to view the breakdown of these costs. Oracle Fusion Projects associates the costs of the resources used for tasks with branches and levels in the resource breakdown structure. The process for determining the correct association is managed by rules of precedence.
Oracle Fusion Projects uses the following rules to associate cost amounts with resources:
Select the lowest level in the resource breakdown structure to which a transaction can map.
If there is only one level to which the transaction maps, the cost amounts are mapped to that level.
If the transaction maps to more than one level, Oracle Fusion Projects sums the precedence numbers for all resource types in the branch and gives precedence to the resource element in the branch with the lowest sum.
If more than one branch has the lowest precedence number at the lower level, the application uses the precedence number of the next level up.
If the sum of precedence numbers is the same for more than one branch, precedence is given to the branch with the lowest number at the lowest level.
If one branch contains a user-defined resource type, precedence is given to the branch that does not contain a user-defined resource type.
Note Oracle Fusion Projects gives more precedence to a lower precedence number. For example, a resource element with a precedence number of 1 is given precedence over a resource element with a precedence number of 10.
NEW QUESTION 5
Identify the precedence order in which cost rates are determined for a planning resource when deriving raw costs for rate-based planning resources. (Choose the best answer.)
Answer: D
Explanation:
Reference https://fusionhelp.oracle.com/helpPortal/topic/TopicId_P_8718794B26A7BB93E040D30A688149A3
NEW QUESTION 6
Your customer wants to automatically allocate unassigned asset lines and common costs across multiple assets based on the construction-in-process cost of each asset. Identify the asset allocation method that you must use as the default method while configuring project types to meet this requirement. (Choose the best answer.)
Answer: C
Explanation:
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapfm/project-foundation-configuratio
NEW QUESTION 7
Your customer wants to assign the Net 45 payment term to all sets except for the corporate business unit specific set, which is assigned the Net 15 payment term. At transaction entry, the list of values for payment terms consists of only one set of data: the set that is assigned to the transaction's business unit.
Which reference data sharing method would you set up to meet the customer requirement? (Choose the best answer.)
Answer: D
Explanation:
Reference
https://docs.oracle.com/en/cloud/saas/applications-common/19b/facia/define-enterprise-structures.html#FACIA4
Reference Data Sharing Methods
Variations exist in the methods used to share data in reference data sets across different types of objects. The following list identifies the methods:
Assignment to one set only, no common values allowed. This method is the simplest form of sharing
reference data that allows assigning a reference data object instance to one and only one set. For example, Asset Prorate Conventions are defined and assigned to only one reference data set. This set can be shared across multiple asset books, but all the values are contained only in this one set.
Assignment to one set only, with common values. This method is the most commonly used method of sharing reference data that allows defining reference data object instance across all sets. For example, Receivables Transaction Types are assigned to a common set that is available to all the business units. You need not explicitly assign the transaction types to each business unit. In addition, you can assign a business unit-specific set of transaction types. At transaction entry, the list of values for transaction types includes the following:
Transaction types from the set assigned to the business unit.
Transaction types assigned to the common set that is shared across all business units.
Assignment to multiple sets, no common values allowed. The method of sharing reference data that allows a reference data object instance to be assigned to multiple sets. For instance, Payables Payment Terms use this method. It means that each payment term can be assigned to one or more than one set. For example, you assign the payment term Net 30 to several sets but assign Net 15 to a set specific only to your business unit. At transaction entry, the list of values for payment terms consists of only the set that is assigned to the transaction's business unit.
Note: Oracle Fusion Applications contains a reference data set called Enterprise. Define any reference data that affects your entire enterprise in this set. Also update the data set going forward as you create new reference data items.
NEW QUESTION 8
Which three file-based data imports are available for use in Oracle Project Portfolio Management Cloud?
Answer: ABC
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oefpp/toc.htm
NEW QUESTION 9
While creating a new project template, you notice that a default Asset Cost Allocation method is being automatically associated. Identify the source setup from which the default value is being inherited. (Choose the best answer.)
Answer: B
Explanation:
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapjf/define-project.html#OAPJF2201
Asset Cost Allocation Methods
The asset cost allocation method determines how indirect or common costs incurred on a project are allocated to multiple assets.
You can specify an asset cost allocation method to enable Oracle Fusion Project Costing to automatically allocate unassigned asset lines and common costs across multiple assets. Unassigned asset lines typically occur when more than one asset is assigned to an asset grouping level.
Projects and project templates inherit a default asset cost allocation method from the associated project type. You can override the default at the project level. If you use capital events to allocate costs, then you can also override the asset cost allocation method at the event level
Asset Cost Allocation Methods
The following table describes the available asset cost allocation methods. Method
Basis of Cost Allocation
Actual Units
Number of units defined for each asset Current Cost
Construction-in-process (CIP) cost of each asset Estimated Cost
Estimated cost of each asset Standard Unit Cost
Combination of the standard unit cost and the number of units defined for each asset Spread Evenly
Equal allocation of cost to each asset
NEW QUESTION 10
Which three setups can be configured by using Rapid Implementation for Project Financial Management Applications?
Answer: ABD
NEW QUESTION 11
You have a billable project for which the following details are provided: Associated Inception-To-Date (ITD) Project Actual Cost: USD 60
Associated Project Budgeted Cost: USD 300 Contract Amount: USD 1000
Project Funded Amount: USD 750
Sum of Existing Revenue Events: USD 80
Identify the Associated Project Spent revenue that will get generated based on the preceding details. (Choose the best answer.)
Answer: D
Explanation:
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapjb/manage-project-contract-revenue
Associated Project Percent Spent Example
The following formula calculates the percent spent revenue for the associated project.
((Sum of ITD Actual Cost for every subtask that is part of the associated task / Sum of Total Budgeted cost for every task that is part of associated task)
x Associated Project Funded Amount) – Sum of Existing Invoice Event Amounts for the Associated Project ((60/300) x 750) – 80 = 70
((Actual Cost / Budgeted Cost) x Budgeted Revenue) – Sum of Revenue Event Amount
NEW QUESTION 12
Identify the three contract attributes from Project Performance Data that are used in Project Performance dashboard regions. (Choose three.)
Answer: BCE
Explanation:
Reference https://docs.oracle.com/cloud/farel9/projectcs_gs/FAUAR/F1537947AN10251.htm
NEW QUESTION 13
Identify the valid approval group type applicable to Oracle Project Financial Management Cloud. (Choose the best answer.)
Answer: C
Explanation:
Ref:
https://docs.oracle.com/en/cloud/saas/applications-common/19b/facia/define-approval-management.html#FACI
NEW QUESTION 14
Identify the attribute of a project type that determines if expenditure items are billable, and the amount type to be used as the basis for transfer pricing. (Choose the best answer.)
Answer: A
Explanation:
Reference https://docs.oracle.com/cloud/latest/projectcs_gs/OAPFM/OAPFM1125361.htm#OAPFM1125277 (what’s a work type?)
In billing, you can use work types to classify work for the following purposes:
To determine the default billable status of expenditure items.
To classify cross-charge amounts into cost and revenue for cross-charge transactions.
Tip: To use work types to determine whether an expenditure item is billable you must set the profile option Work Type Derived for Expenditure Item to Yes.
When you create or import expenditure items, the default work type is inherited from the associated task. Tasks, in turn, inherit work type values from parent tasks and ultimately from the project. Project types determine the default work type value for projects and project templates.
NEW QUESTION 15
In your customer site, the capitalized interest calculation is implemented on their project types. Which option represents the costs considered in the interest calculation? (Choose the best answer.)
Answer: E
Explanation:
Reference https://fusionhelp.oracle.com/helpPortal/topic/TopicId_P_988B43C997365159E040D30A68813832
https://docs.oracle.com/cd/E48434_01/fusionapps.1118/e49622/F1125377AN61D92.htm
NEW QUESTION 16
Your customer wants to generate accounting based on project information associated with the transaction for all subledger transactions. Identify three subledger applications for which the project source is available for deriving accounts when configuring subledger accounting. (Choose three.)
Answer: ABD
Explanation:
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapfm/project-costing-configuration-de
NEW QUESTION 17
You want to export your project plan to Oracle Project Financial Management Cloud after initial scheduling is complete in Microsoft Projects. Identify three conditions that must be met for exporting milestone tasks. ( Choose three.)
Answer: CDE
Explanation:
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapex/define-project-management-conf
NEW QUESTION 18
You have closed the project accounting period with a warning, but you are unable to close the accounting period due to an error.
Identify two reasons for this problem. (Choose two.)
Answer: BE
Explanation:
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapjb/record-accounting-for-project-bil
NEW QUESTION 19
A project administrator is trying to assign a team member for a project but cannot find the person in the team member list on the Project Definition page. What is the reason for this problem? (Choose the best answer.)
Answer: D
Explanation:
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapfm/project-foundation-configuratio
Why can't I find persons in the list of resources when I enter team members, planning resources, or person rate schedules?
You can't find persons in the list of resources when you enter team members, planning resources, or person rate schedules in the following situations:
The administrator didn't assign a department while creating users. Persons must have an active assignment and be assigned to a department in Oracle Fusion Human Capital Management before they can be added as team members or entered as resources on the planning resource breakdown structure or person rate schedule.
The resource isn't active in Oracle Fusion Human Capital Management because the current date is before the effective date of the resource. If you want to include persons who will start in the future, select the Include people with future-dated effective start dates option when you search for the person.
Persons assigned as project managers aren't active as of the project start date.
The assignment of the person is terminated, and an appropriate value isn't set for the number of days to display people with terminated assignments. You can set the profile value appropriately at the site profile level using the Specify Number of Days to Display People with Terminated Assignments task in the Setup and Maintenance work area.
NEW QUESTION 20
You are set up as a Follower in Manage Tasks. Which two abilities can you accomplish? (Choose two.)
Answer: BC
Explanation:
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapem/execute-project-tasks-and-deliv
Followers are persons who aren't working on the task but have an interest in reviewing the task progress. Only the resources and other followers can add followers to a task. If a resource assigns the task to another team member, the application automatically changes the original resource to a follower.
What's the difference between my tasks and tasks that I follow?
You can edit task details and enter progress for your tasks on the Manage Tasks page. If a task has multiple resources, only the primary resource can edit the task.
When you follow a task, you can view the task details and see the task activity stream. You receive e-mail notifications of changes that team members make to the task.
If a resource reassigns the task to another team member, then the previous resource automatically becomes a follower.
NEW QUESTION 21
......