CAPM Premium Bundle

CAPM Premium Bundle

Certified Associate in Project Management (PMI-100) Certification Exam

4.5 
(53310 ratings)
0 QuestionsPractice Tests
0 PDFPrint version
November 21, 2024Last update

PMI CAPM Free Practice Questions

Exam Code: CAPM (Practice Exam Latest Test Questions VCE PDF)
Exam Name: Certified Associate in Project Management (PMI-100)
Certification Provider: PMI
Free Today! Guaranteed Training- Pass CAPM Exam.

Online CAPM free questions and answers of New Version:

NEW QUESTION 1

Risk responses reflect an organization's perceived balance between:

  • A. risk taking and risk avoidance.
  • B. known risk and unknown risk.
  • C. identified risk and analyzed risk.
  • D. varying degrees of ris

Answer: A

NEW QUESTION 2

In which process might a project manager use risk reassessment as a tool and technique?

  • A. Perform Qualitative Risk Analysis
  • B. Monitor and Control Risk
  • C. Monitor and Control Project Work
  • D. Plan Risk Responses

Answer: B

NEW QUESTION 3

What is the term assigned to products or services having the same functional use but different technical characteristics?

  • A. Scope
  • B. Quality
  • C. Specification
  • D. Grade

Answer: D

NEW QUESTION 4

An input to the Plan Stakeholder Management process is:

  • A. The project charter.
  • B. The stakeholder analysis.
  • C. A communication management plan.
  • D. A stakeholder registe

Answer: D

NEW QUESTION 5

Which tools or techniques will a project manager use for Develop Project Team?

  • A. Negotiation
  • B. Roles and responsibilities
  • C. Recognition and rewards
  • D. Prizing and promoting

Answer: C

NEW QUESTION 6

Which can be used to determine whether a process is stable or has predictable performance?

  • A. Matrix diagram
  • B. Histogram
  • C. Control chart
  • D. Flowchart

Answer: C

NEW QUESTION 7

Which process involves subdividing project deliverables and project work into smaller, more manageable portions?

  • A. Develop Schedule
  • B. Create VVBS
  • C. Estimate Activity Resources
  • D. Define Scope

Answer: B

NEW QUESTION 8

Co-location is a tool and technique of:

  • A. Develop Human Resource Plan.
  • B. Manage Project Team.
  • C. Develop Project Team.
  • D. Acquire Project Tea

Answer: C

NEW QUESTION 9

Which document includes the project scope, major deliverables, assumptions, and constraints?

  • A. Project charter
  • B. Project scope statement
  • C. Scope management plan
  • D. Project document updates

Answer: B

NEW QUESTION 10

A temporary endeavor that creates a unique product or service is called a:

  • A. Project
  • B. Plan
  • C. Program
  • D. Portfolio

Answer: A

NEW QUESTION 11

Which type of analysis would be used for the Plan Quality process?

  • A. Schedule
  • B. Checklist
  • C. Assumption
  • D. Cost-Benefit

Answer: D

NEW QUESTION 12

Which of the following is an example of the simplest fixed-price contract?

  • A. Purchase requisition
  • B. Purchase order
  • C. Verbal agreement
  • D. Request for quote

Answer: B

NEW QUESTION 13

An input to the Plan Procurement Management process is:

  • A. Source selection criteria.
  • B. Market research.
  • C. A stakeholder register.
  • D. A records management syste

Answer: C

NEW QUESTION 14

Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?

  • A. Project document updates
  • B. Activity list
  • C. Activity attributes
  • D. Project calendars

Answer: C

NEW QUESTION 15

An input required in Define Scope is an organizational:

  • A. structure.
  • B. process asset.
  • C. matrix.
  • D. breakdown structur

Answer: B

NEW QUESTION 16

Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be
involved in a project?

  • A. Feedback analysis
  • B. Stakeholder analysis
  • C. Communication management plan
  • D. Stakeholder management plan

Answer: D

NEW QUESTION 17

An input to the Plan Cost Management process is:

  • A. Cost estimates.
  • B. Resource calendars,
  • C. The project charter,
  • D. The risk registe

Answer: C

NEW QUESTION 18

A project management office manages a number of aspects including the:

  • A. Project scope, schedule, cost, and quality of the products of the work packages.
  • B. Central coordination of communication management across projects.
  • C. Assignment of project resources to best meet project objectives.
  • D. Overall risk, overall opportunity, and interdependencies among projects at the enterprise leve

Answer: D

NEW QUESTION 19

A tool and technique used in the Develop Project Charter process is:

  • A. change control tools
  • B. expert judgment
  • C. meetings
  • D. analytical techniques

Answer: B

NEW QUESTION 20

Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific
sequence is desired, even though there may be other acceptable sequences?

  • A. External
  • B. Internal
  • C. Mandatory
  • D. Discretionary

Answer: D

NEW QUESTION 21

The process of prioritizing risks for further analysis or action is known as:

  • A. Plan Risk Management.
  • B. Plan Risk Responses.
  • C. Perform Qualitative Risk Analysis.
  • D. Perform Quantitative Risk Analysi

Answer: C

NEW QUESTION 22

Which Process Group and Knowledge Area include the Sequence Activities process?

  • A. Executing Process Group and Project Time Management
  • B. Executing Process Group and Project Cost Management
  • C. Planning Process Group and Project Time Management
  • D. Planning Process Group and Project Cost Management

Answer: C

NEW QUESTION 23

Which of the following characteristics are found in a functional organizational structure?

  • A. Little or no project manager authority, little or no resource availability, and the functional manager controls the project budget
  • B. Limited project manager authority, limited resource availability, and a part-time project manager's role
  • C. Low to moderate project manager authority, low to moderate resource availability, and a full-time project manager's role
  • D. High to almost total project manager authority, high to almost total resource availability, and full-time project management administrative staff

Answer: A

NEW QUESTION 24

Which project document is updated in the Control Stakeholder Engagement process?

  • A. Project reports
  • B. Issue log
  • C. Lessons learned documentation
  • D. Work performance information

Answer: B

NEW QUESTION 25

What are the Project Procurement Management processes?

  • A. Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements
  • B. Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements
  • C. Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements
  • D. Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements

Answer: C

NEW QUESTION 26
......

100% Valid and Newest Version CAPM Questions & Answers shared by Certleader, Get Full Dumps HERE: https://www.certleader.com/CAPM-dumps.html (New 704 Q&As)


START CAPM EXAM