Your success in PMI CAPM is our sole target and we develop all our CAPM braindumps in a way that facilitates the attainment of this target. Not only is our CAPM study material the best you can find, it is also the most detailed and the most updated. CAPM Practice Exams for PMI CAPM are written to the highest standards of technical accuracy.

Free CAPM Demo Online For PMI Certifitcation:

NEW QUESTION 1

Progressively elaborating high-level information into detailed plans is performed by the:

  • A. project management office
  • B. portfolio manager
  • C. program manager
  • D. project manager

Answer: D

NEW QUESTION 2

High-level project risks are included in which document?

  • A. Business case
  • B. Risk breakdown structure
  • C. Project charter
  • D. Risk register

Answer: C

NEW QUESTION 3

A project manager should document the escalation path for unresolved project risks in the:

  • A. Change control plan
  • B. Stakeholder register
  • C. Risk log
  • D. Communications management plan

Answer: D

NEW QUESTION 4

Monte Carlo is which type of risk analysis technique?

  • A. Probability
  • B. Quantitative
  • C. Qualitative
  • D. Sensitivity

Answer: B

NEW QUESTION 5

Which tool or technique is used in validating the scope of a project?

  • A. Facilitated workshops
  • B. Interviews
  • C. Inspection
  • D. Meetings

Answer: C

NEW QUESTION 6

A large portion of a projects budget is typically expended on the processes in which Process Group?

  • A. Executing
  • B. Planning
  • C. Monitoring and Controlling
  • D. Closing

Answer: B

NEW QUESTION 7

When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?

  • A. Authority
  • B. Role
  • C. Competency
  • D. Responsibility

Answer: C

NEW QUESTION 8

A regression line is used to estimate:

  • A. Whether or not a process is stable or has predictable performance.
  • B. How a change to the independent variable influences the value of the dependent variable.
  • C. The upper and lower specification limits on a control chart.
  • D. The central tendency, dispersion, and shape of a statistical distributio

Answer: B

NEW QUESTION 9

In which type of organizational structure are staff members grouped by specialty?

  • A. Functional
  • B. Projectized
  • C. Matrix
  • D. Balanced

Answer: A

NEW QUESTION 10

Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?

  • A. Scope audits
  • B. Scope reviews
  • C. Quality audits
  • D. Control chart

Answer: C

NEW QUESTION 11

At which stage of team development do members begin to work together, adjust work habits, and trust each other?

  • A. Forming
  • B. Storming
  • C. Norming
  • D. Performing

Answer: C

NEW QUESTION 12

In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?

  • A. Start-to-start (SS)
  • B. Start-to-finish (SF)
  • C. Rnish-to-finish (FF)
  • D. Finish-to-start (FS)

Answer: D

NEW QUESTION 13

Which item is a cost of conformance?

  • A. Training
  • B. Liabilities
  • C. Lost business
  • D. Scrap

Answer: A

NEW QUESTION 14

For a stakeholder with low interest and high power, the project manager should:

  • A. Monitor the stakeholder.
  • B. Manage the stakeholder closely.
  • C. Keep the stakeholder satisfied.
  • D. Keep the stakeholder informe

Answer: C

NEW QUESTION 15

Which of the following is an output from Control Scope?

  • A. Change requests
  • B. Variance analysis
  • C. Accepted deliverables
  • D. Requirements documentation

Answer: A

NEW QUESTION 16

In a weak matrix, the project managers role is:

  • A. part-time
  • B. full-time
  • C. occasional
  • D. unlimited

Answer: A

NEW QUESTION 17

The component of the risk management plan that documents how risk activities will be recorded is called:

  • A. tracking
  • B. scoping
  • C. timing
  • D. defining

Answer: A

NEW QUESTION 18

Which is used to solicit proposals from prospective sellers?

  • A. Procurement statement of work
  • B. Resource calendars
  • C. Procurement document
  • D. Independent estimates

Answer: C

NEW QUESTION 19

Which process requires implementation of approved changes?

  • A. Direct and Manage Project Execution
  • B. Monitor and Control Project Work
  • C. Perform Integrated Change Control
  • D. Close Project or Phase

Answer: A

NEW QUESTION 20

Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?

  • A. Enhance
  • B. Share
  • C. Exploit
  • D. Accept

Answer: C

NEW QUESTION 21

The process improvement plan details the steps for analyzing processes to identify activities which enhance their:

  • A. quality.
  • B. value.
  • C. technical performance.
  • D. statu

Answer: B

NEW QUESTION 22

The procurement process that documents agreements and related documentation for future reference is known as:

  • A. Plan Procurements.
  • B. Control Procurements.
  • C. Close Procurements.
  • D. Conduct Procurement

Answer: C

NEW QUESTION 23

When can pre-assignment of project team members occur?

  • A. When the project uses capital expenditures
  • B. When the required staff can be acquired from outside sources
  • C. When the project would be ignored due to travel expenses
  • D. When the project is the result of specific people being promised as part of a competitive proposal

Answer: D

NEW QUESTION 24

Risk categorization is a tool or technique used in which process?

  • A. Plan Risk Responses
  • B. Plan Risk Management
  • C. Perform Qualitative Risk Analysis
  • D. Perform Quantitative Risk Analysis

Answer: C

NEW QUESTION 25

A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:

  • A. triangular distribution
  • B. tornado diagram
  • C. beta distribution
  • D. fishbone diagram

Answer: B

NEW QUESTION 26
......

P.S. Dumps-hub.com now are offering 100% pass ensure CAPM dumps! All CAPM exam questions have been updated with correct answers: https://www.dumps-hub.com/CAPM-dumps.html (704 New Questions)