Pass4sure CAPM Questions are updated and all CAPM answers are verified by experts. Once you have completely prepared with our CAPM exam prep kits you will be ready for the real CAPM exam without a problem. We have Renewal PMI CAPM dumps study guide. PASSED CAPM First attempt! Here What I Did.
Online PMI CAPM free dumps demo Below:
NEW QUESTION 1
Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?
Answer: B
NEW QUESTION 2
Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?
Answer: C
NEW QUESTION 3
Which organizational process assets update is performed during the Close Procurements process?
Answer: B
NEW QUESTION 4
During which process group is the quality policy determined?
Answer: C
NEW QUESTION 5
Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?
Answer: B
NEW QUESTION 6
Which is a tool or technique used in Define Scope?
Answer: C
NEW QUESTION 7
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
Answer: C
NEW QUESTION 8
Which tool or technique is an examination of industry and specific vendor capabilities?
Answer: B
NEW QUESTION 9
Which is one of the major outputs of Sequence Activities?
Answer: C
NEW QUESTION 10
In the Plan Stakeholder Management process, expert judgment is used to:
Answer: D
NEW QUESTION 11
The progressive detailing of the project management plan is called:
Answer: B
NEW QUESTION 12
Which type of chart is a graphic representation of a process showing the relationships among process steps?
Answer: C
NEW QUESTION 13
The ability to influence cost is greatest during which stages of the project?
Answer: A
NEW QUESTION 14
In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?
Answer: C
NEW QUESTION 15
Stakeholder satisfaction should be managed as a key project:
Answer: C
NEW QUESTION 16
Which activity is an input to the Conduct Procurements process?
Answer: A
NEW QUESTION 17
A collection of projects managed as a group to achieve strategic objectives is referred to as a:
Answer: D
NEW QUESTION 18
As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?
Answer: B
NEW QUESTION 19
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
Answer: B
NEW QUESTION 20
Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?
Answer: B
NEW QUESTION 21
Typical outcomes of a project include:
Answer: A
NEW QUESTION 22
Which of the following is a tool or technique used in the Determine Budget process?
Answer: D
NEW QUESTION 23
When is a project finished?
Answer: C
NEW QUESTION 24
Which of the following is an input to Control Scope?
Answer: D
NEW QUESTION 25
Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?
Answer: C
NEW QUESTION 26
......
P.S. Easily pass CAPM Exam with 704 Q&As Dumps-hub.com Dumps & pdf Version, Welcome to Download the Newest Dumps-hub.com CAPM Dumps: https://www.dumps-hub.com/CAPM-dumps.html (704 New Questions)