CAPM Premium Bundle

CAPM Premium Bundle

Certified Associate in Project Management (PMI-100) Certification Exam

4.5 
(53340 ratings)
0 QuestionsPractice Tests
0 PDFPrint version
September 29, 2024Last update

PMI CAPM Free Practice Questions

Pass4sure CAPM Questions are updated and all CAPM answers are verified by experts. Once you have completely prepared with our CAPM exam prep kits you will be ready for the real CAPM exam without a problem. We have Renewal PMI CAPM dumps study guide. PASSED CAPM First attempt! Here What I Did.

Online PMI CAPM free dumps demo Below:

NEW QUESTION 1

Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?

  • A. Organizational process updates
  • B. Quality metrics
  • C. Change requests
  • D. Quality control measurements

Answer: B

NEW QUESTION 2

Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?

  • A. Compromising
  • B. Collaborating
  • C. Smoothing
  • D. Problem Solving

Answer: C

NEW QUESTION 3

Which organizational process assets update is performed during the Close Procurements process?

  • A. Procurement audit
  • B. Lessons learned
  • C. Performance reporting
  • D. Payment requests

Answer: B

NEW QUESTION 4

During which process group is the quality policy determined?

  • A. Initiating
  • B. Executing
  • C. Planning
  • D. Controlling

Answer: C

NEW QUESTION 5

Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?

  • A. The influence of the stakeholders increases, the cost of changes increases.
  • B. The influence of the stakeholders decreases, the cost of changes increases.
  • C. The influence of the stakeholders increases, the cost of changes decreases.
  • D. The influence of the stakeholders decreases, the cost of changes decrease

Answer: B

NEW QUESTION 6

Which is a tool or technique used in Define Scope?

  • A. Templates, forms, and standards
  • B. Change requests
  • C. Product analysis
  • D. Project assumptions

Answer: C

NEW QUESTION 7

A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?

  • A. Three weeks
  • B. Four weeks
  • C. Five weeks
  • D. Six weeks

Answer: C

NEW QUESTION 8

Which tool or technique is an examination of industry and specific vendor capabilities?

  • A. Independent estimates
  • B. Market research
  • C. Analytical techniques
  • D. Bidder conferences

Answer: B

NEW QUESTION 9

Which is one of the major outputs of Sequence Activities?

  • A. Responsibility assignment matrix (RAM)
  • B. Work breakdown structure (WBS) update
  • C. Project schedule network diagram
  • D. Mandatory dependencies list

Answer: C

NEW QUESTION 10

In the Plan Stakeholder Management process, expert judgment is used to:

  • A. Provide information needed to plan appropriate ways to engage project stakeholders.
  • B. Ensure comprehensive identification and listing of new stakeholders.
  • C. Analyze the information needed to develop the project scope statement.
  • D. Decide the level of engagement of the stakeholders at each required stag

Answer: D

NEW QUESTION 11

The progressive detailing of the project management plan is called:

  • A. expert judgment.
  • B. rolling wave planning.
  • C. work performance information.
  • D. specificatio

Answer: B

NEW QUESTION 12

Which type of chart is a graphic representation of a process showing the relationships among process steps?

  • A. Control
  • B. Bar
  • C. Flow
  • D. Pareto

Answer: C

NEW QUESTION 13

The ability to influence cost is greatest during which stages of the project?

  • A. Early
  • B. Middle
  • C. Late
  • D. Completion

Answer: A

NEW QUESTION 14

In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

  • A. Performing
  • B. Storming
  • C. Norming
  • D. Forming

Answer: C

NEW QUESTION 15

Stakeholder satisfaction should be managed as a key project:

  • A. Benefit
  • B. Initiative
  • C. Objective
  • D. Process

Answer: C

NEW QUESTION 16

Which activity is an input to the Conduct Procurements process?

  • A. Organizational process assets
  • B. Resource availability
  • C. Perform Integrated Change Control
  • D. Team performance assessment

Answer: A

NEW QUESTION 17

A collection of projects managed as a group to achieve strategic objectives is referred to as a:

  • A. plan
  • B. process
  • C. program
  • D. portfolio

Answer: D

NEW QUESTION 18

As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?

  • A. BAC
  • B. EAC
  • C. ETC
  • D. WBS

Answer: B

NEW QUESTION 19

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

  • A. Applying calendars
  • B. Resource leveling
  • C. Resource planning
  • D. Resource conflict management

Answer: B

NEW QUESTION 20

Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

  • A. Critical path method
  • B. Critical chain method
  • C. Resource leveling
  • D. Schedule network analysis

Answer: B

NEW QUESTION 21

Typical outcomes of a project include:

  • A. Products, services, and improvements.
  • B. Products, programs, and services.
  • C. Improvements, portfolios, and services.
  • D. Improvements, processes, and product

Answer: A

NEW QUESTION 22

Which of the following is a tool or technique used in the Determine Budget process?

  • A. Variance analysis
  • B. Three-point estimating
  • C. Bottom-up estimating
  • D. Historical relationships

Answer: D

NEW QUESTION 23

When is a project finished?

  • A. After verbal acceptance of the customer or sponsor
  • B. After lessons learned have been documented in contract closure
  • C. When the project objectives have been met
  • D. After resources have been released

Answer: C

NEW QUESTION 24

Which of the following is an input to Control Scope?

  • A. Project schedule
  • B. Organizational process assets updates
  • C. Project document updates
  • D. Work performance information

Answer: D

NEW QUESTION 25

Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?

  • A. Internal
  • B. External
  • C. Discretionary
  • D. Mandatory

Answer: C

NEW QUESTION 26
......

P.S. Easily pass CAPM Exam with 704 Q&As Dumps-hub.com Dumps & pdf Version, Welcome to Download the Newest Dumps-hub.com CAPM Dumps: https://www.dumps-hub.com/CAPM-dumps.html (704 New Questions)


START CAPM EXAM