Q1. Which of the following does TOGAF describe as "a formal description of a system, or a detailed plan of the system at component level to guide its implementation"?
A. Architecture
B. Artifact
C. Deliverable
D. Model
E. View
Answer: A
Explanation:
Q2. Scenario
Please read this scenario prior to answering the Question
You are serving as the Lead Architect for an insurance company, which has been formed through the merger of three previously independent companies. The company now consists of three divisions with the same names and division headquarters as their predecessors.
The lack of integration between the three divisions has increasingly caused problems in the handling of customer and financial information. The inability to share information has resulted in lost opportunities to "leverage the synergies" that had been intended when the company was formed. At present, each division maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, and claims Information, each division has different ways of defining these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.
As a result, the company has made the decision to introduce a common web portal, contact center software suite, and document management system. Also the company has selected a single enterprise-wide customer relationship management (CRM) application to consolidate information from several applications that exist across the divisions. The application will be used by each of the divisions and accessed by third party partners through well defined interfaces.
The Corporate Board is concerned that the new application must be able to manage and safeguard confidential customer information in a secure manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services in cooperation with its partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the implementation team and the migration teams in each division. The CIO has also formed a cross-functional Architecture Board to oversee and govern the architecture. The company has an existing team of security architects.
TOGAF 9 has been selected as the core framework for use for the Enterprise Architecture program. The CIO has endorsed this choice with the full support of top management.
Refer to the Scenario
In the Preliminary Phase you need to define suitable policies and ensure that the company has the appropriate capability to address the concerns of the Corporate Board.
Based on TOGAF, which of the following is the best answer?
A. You evaluate the implications of the concerns raised by the Corporate Board in terms of regulatory requirements and their impact on business goals and objectives. Based on this understanding, you then issue a Request for Architecture Work to commence an architecture development project to develop a solution that will address the concerns. You allocate a security architect to oversee the implementation of the new application that is being developed.
B. You start by clarifying the intent that the Board has for raising these concerns. This enables you to understand the implications of the concerns in terms of regulatory requirements and the potential impact on current business goals and objectives. You propose that a security architect or security architecture team be allocated to develop a comprehensive security architecture and that this be considered an additional domain architecture.
C. You evaluate the implications of the Board's concerns by examining the security and regulatory impacts on business goals, business drivers and objectives. Based on your understanding, you then update the current security policy to include an emphasis on the concerns. You define architecture principles to form constraints on the architecture work to be undertaken in the project. You then allocate a security architect to ensure that security considerations are included in the architecture planning for all domains.
D. You identify and document the security and regulatory requirements for the application and the data being collected. You ensure that written policies are put in place to address the requirements, and that they are communicated across the organization, together with appropriate training for key employees. You identify constraints on the architecture and communicate those to the architecture team. You establish an agreement with the security architects defining their role within the ongoing architecture project.
Answer: D
Explanation:
Q3. Scenario:
Please read this scenario prior to answering the Question
You are serving as the Lead Architect for the enterprise architecture team at the prime contractor for the Dreadnought Unmanned Aircraft System program.
Over the course of this contract, the company has grown rapidly by acquisition and has inherited numerous different procurement processes and related IT systems. The decision has been made to consolidate and reduce redundant procurement processes and systems. The CEO has announced that the company will seek to leverage higher volume discounts and lower related IT support costs by instituting a preferred supplier program.
TOGAF 9 Is used for internal Enterprise Architecture activities, with an iterative approach for executing Architecture Development Method (ADM) projects.
At present, there are no particularly useful architectural assets related to this initiative, so all assets need to be acquired and customized or created from scratch. The company prefers to implement commercial off the shelf package applications with little customization. The CIO, who is the project sponsor, has stated that she is not concerned about preserving existing processes or systems.
The architect-re development project has put in place Its Architecture Capability for this project and has started a number of iteration cycles to develop the Architecture. Some tasks to address concerns related to the Business Architecture have been completed. The next immediate task is to address the Information Systems Architectures.
The Information Systems Architectures must address stakeholder concerns such as:
1. Which procurement-related business processes are supported by zero, one, or many existing applications?
2. What non-procurement applications will need to be integrated with any new procurement applications?
3. What data will need to be shared?
Refer to the Scenario
[Note: You may need to refer to TOGAF 9 Chapter 35 in order to answer this question.]
You have been asked to identify the most appropriate catalogs, matrices, and diagrams for this situation.
Based on TOGAF 9, which of the following is the best answer?
A. in the early iterations of Architecture development, you would describe the Baseline Application Architecture with a System/Function matrix, and describe the Baseline Data Architecture using a Data Entity/Data Component catalog. In the later Iterations of the Architecture Definition, you would describe the Target Application Architecture using Application Communication diagrams and an Application Interaction matrix, and describe the Target Data Architecture with a System/Data matrix.
B. In the early iterations of Architecture development, you would describe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrix, and describe the Target Data Architecture with a System/Data matrix. In the later iterations of Architecture development, you would describe the Baseline Application Architecture with an Application and User Location diagram and a System/Function matrix, and describe the Baseline Data Architecture with a Data Entity/Data Component catalog.
C. In the early iterations of Architecture development, you would describe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrix, and describe the Target Data Architecture with a Data Entity/Business Function matrix and a System/Data matrix. In the later iterations of Architecture development, you would describe the Baseline Application Architecture with a System/Function matrix, and describe the Baseline Data Architecture with a Data Entity/Data Component catalog.
D. In the early iterations of Architecture development, you would describe the Baseline Application Architecture with a Technology Portfolio catalog, and describe the Baseline Data Architecture with a Data diagram. In the later iterations of Architecture development, you would describe the Target Application Architecture with a System/Technology matrix, and describe the Target Data Architecture with a Data Dissemination diagram.
Answer: C
Explanation: In this the company prefers to implement commercial off the shelf package application with little customization and not concerned about preserving existing processes or systems.
Reference: 19.4 Approaches to Architecture Development.
Q4. According to TOGAF, which of the following best describes how the Enterprise Continuum is used in organizing and developing an architecture?
A. It is used to coordinate with the other management frameworks in use
B. It is used to describe how an architecture addresses stakeholder concerns
C. It is used to identify and understand business requirements
D. It is used to provide a system for continuous monitoring
E. It is used to structure re-usable architecture and solution assets
Answer: E
Explanation:
Q5. Scenario
Please read this scenario prior to answering the Question
You are working as a consultant to the Chief Architect at a government agency responsible for securing all government communications and information systems. The agency has recently received funding for a program that will upgrade the reliability and performance of its secure communication systems which provide real-time, highly secure communication of voice, video, and message data to remote locations around the world.
The agency has an established enterprise architecture (EA) capability based on TOGAF 9. The Executive Director of the agency is the sponsor of the EA capability.
Since reliable, high-performance, and secure communications are essential to preserving national security, the Executive Director has placed more stringent requirements for the architecture for the upgraded system. It must be able to provide assurance and verification of specific performance measures on the key services that are most crucial for system operation. Focusing on these service-level details and specific measurements will allow more stringent requirements to be enforced in service contracts. It will also provide a high degree of assurance that necessary performance is being delivered and that notifications will occur if any critical service fails to perform as required.
A portion of the program budget has been allocated to context a review of the EA. The scope of the review is to evaluate the processes, content and governance of the EA capability to ensure that the higher target performance and service levels required by the upgraded system can be achieved.
The Chief Architecture has noted that the core EA artifacts that have been used since TOGAF 9 was introduced are not adequate to describe these new capabilities. The artifacts do not have explicit provisions for defining the in-depth measurement requirements regarding specific services required for the system. She has learned that certain services within the current system have service measurement implementations that match some of the new requirements, but they are only used in a few areas.
Recent EA efforts at another national agency have produced generalized high-performance communication system models to realize similar requirements in a critical defense system involving secure communications. It is possible that these models may be useful for the upgrade program.
Refer to the Scenario
You have been asked to make recommendations for tailoring the Architecture Content Metamodel to accommodate the requirements of the upgraded system.
Based on TOGAF, which of the following is the best answer?
A. Since some artifacts will now require specific measurements and additional data will be needed to support the performance objectives linked to these measurements, you recommend that the motivation and governance extensions of the TOGAF 9 Content Metamodel are used. Using these extensions will allow modeling the goals, objectives and drivers for the architecture, linking them to service levels and more detailed governance models. This will also enable the ability to re-use existing profiles, customizing them for the various service contracts involved.
B. You recommend all of the TOGAF 9 Content Metamodel extensions be incorporated into the Architecture Content Metamodel. The full Content Metamodel will enable the EA team to capture and categorize all the important additional data needs to support the performance and measurement objectives linked to these artifacts. Once the new repository content has been implemented, on- demand queries can be used to generate a customized governance stakeholder view that isolates the artifacts and data needed to assess measurement for any particular service. If this view is found to be inadequate for the governance concerns, the service models within those artifacts can be expanded.
C. Since this case requires extensions of the modeling and data details of the service, this is best done by using the services extension of the TOGAF 9 Content Metamodel. By using this extension, the service model is no longer constrained by what is expected in typical business service definitions, allowing more flexibility for adding customized models to support the more stringent measurement requirements. The services extension can also be used to map terminology between the business services and the application components.
D. To support the type of stringent performance measurements needed for the more detailed governance views required for the upgraded system, the interfaces to the communication and network layer of the architecture must be highly visible at the application level. To accommodate the proper development of this, a Communications Engineering view should be created from the infrastructure extension models of the TOGAF Content Metamodel. This view will allow architects to align the required performance measurement communications across the system.
Answer: A
Explanation:
Q6. Scenario
Please read this scenario prior to answering the Question
Your role is that of Lead Enterprise Architect within the staff headquarters of a large hotel chain. The chain manages over 500 hotels across North America and Canada, with another 230 hotels internationally in the United Kingdom, Europe, Australia and New Zealand. Unlike other hotel chains, which are often a mix of company-owned and franchised units, each hotel in the chain is an independently owned and operated franchise. Many of the hotels use the same internal IT systems that they used before they joined the franchise. Until recently, the only requirement that has been placed on each hotel is that they use a standard financial reporting system to report their financial results to the headquarters on a weekly basis.
The CEO of the chain has stated his concerns about the inefficiencies of the current approach and identified the need to change. He has defined a new strategic vision that will enhance the business by providing its franchisees new support services including worldwide reservations, global, national and regional marketing as well as consolidated financial, logistics, and yield management. This strategy is part of the long-term commitment to enhance the brand image and drive superior revenue for the chain. He has also stated that he expects improved financial results by the end of the current fiscal year.
These changes will provide the chain with improved utilization of its capacity and more efficient operations. The addition of a corporate-wide data warehouse will provide analytics that will enable the marketing group to improve its ability to target advertising into key national and regional markets to improve yields.
The chain has a mature enterprise architecture practice based in its headquarters and uses TOGAF 9 as the method and guiding framework. The CIO is the sponsor of the activity.
In planning this change, the Chief Architect engaged the services of a well-known consulting firm that specializes in business strategy. An initial study has been conducted to identify the strategic changes needed to implement the CEO's vision. This recently completed with approval of a strategic architecture encompassing the entire chain, including detailed requirements and recommendations.
Based on the recommendations from the initial study, the chain has taken the decision to adopt a packaged suite of integrated applications that is tailored to the needs of the hospitality industry.
Refer to the scenario
You have been asked by the Chief Architect to propose the best approach for architecture development to realize the CEO's vision.
Based on TOGAF, which of the following is the best answer?
A. You propose that this engagement define the baseline Technology Architecture first in order to assess the current infrastructure capacity and capability. Then the focus should be on transition planning and architecture deployment. This will identify requirements to ensure that the projects are sequenced in an optimal fashion so as to realize the vision.
B. You propose that the target architecture is defined first, followed by transition planning. This is because the vision is well understood and the strategic architecture agreed. The target first approach will ensure that the current problems and inefficiencies of the baseline architecture are not carried forward, and that the proposed solution addresses the requirements identified in the initial study.
C. You propose that the team focus on architecture definition, with a specific emphasis on understanding the strategic change parameters of the business strategy. Once understood, the team will be in the best position to identify the requirements, drivers, issues, and constraints for this engagement. You would ensure that the target architecture addresses non-functional requirements so as to ensure the target architecture is robust and secure.
D. You propose that the team focus on defining the target architecture by going through the architecture definition phases (B-D). This is because the initial study identified the need to change. This will ensure that the change can be defined in a structured manner and address the requirements needed to realize the vision.
Answer: B
Explanation:
Q7. Which ADM phase provides architectural oversight of the implementation?
A. Preliminary Phase
B. Phase A
C. Phase E
D. Phase G
E. Phase H
Answer: D
Explanation:
Q8. Which of the following does TOGAF describe as a package of functionality defined to meet business needs across an organization?
A. An application
B. An architecture viewpoint
C. A building block
D. A deliverable
E. A solution architecture
Answer: C
Explanation:
Q9. Scenario:
Please read this scenario prior to answering the question
You are the Lead Enterprise Architect in a company that specializes in the development of wind turbine blades for use in large-scale commercial wind energy production systems. The company has manufacturing facilities located in Illinois, Nebraska, and Manitoba. Each of these plants supplies a different manufacturer that builds and sells complete systems. The turbine blades are custom engineered to meet each manufacturer's design specifications.
Until recently, most turbine blades were fabricated manually using molded fiber-reinforced plastics. However, recent improvements in composite materials, coupled with enhanced automated methods for precision application of materials during the molding process, have led to significant reduction in weight, increase in strength, and improved blade longevity. The company has pioneered the development of a proprietary automated process for continuous extrusion of the turbine blades. Patents have been filed to protect the process, but certain trade secrets must be closely guarded.
The company has a mature Enterprise Architecture organization that is supported by a cross-functional Architecture Board. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.
TOGAF 9 and its Architecture Development Method (ADM) are used to develop the automated manufacturing processes and systems that are used to design, manufacture, and test the blade assemblies.
Recently, a pilot architecture project was completed at a single location that defined a standard approach for controlling the Automated Test System that is used at each plant to perform final quality assurance tests on each completed blade assembly. The Architecture Board approved the plan for immediate implementation at each plant.
Architecture Contracts have been developed that detail the work needed to implement and deploy the new Automated Test System controller for each location. The Chief Engineer, sponsor of the activity, has expressed concern that a uniform process be employed at each location to ensure consistency.
Refer to the Scenario
You have been asked to recommend the best approach to address the Chief Engineer's concern.
Based on TOGAF 9, which of the following is the best answer?
A. You review the applicable Architecture Contract for each location, ensuring that it addresses the project objectives, effectiveness metrics, acceptance criteria, and risk management. In cases where the contract is issued to an external party, you ensure that it is a legally enforceable contract. You schedule compliance reviews at key points in the implementation process to ensure that the work is proceeding in accordance with the Architecture Definition. You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
B. You create an Architecture Contract to manage and govern the implementation and migration process at each location. For internal development projects, you issue a memorandum of understanding between the Architecture Board and the implementation organization. For contracts issued to an external party, you ensure that it is a fully enforceable legal contract. You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
C. You create an Architecture Contract to manage and govern the implementation and migration process. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contract. For internal development projects, you decide it is adequate to utilize a memorandum of understanding between the Architecture Board and the implementation organization. You recommend that if a deviation from the Architecture Contract is detected, the Architecture Board grant a dispensation to allow the implementation organization the ability to customize the process to meet their local needs.
D. You use the issued Architecture Contracts to manage the architecture governance processes for the project across the locations. You deploy monitoring tools to assess the performance of the completed blade assembly at each location and develop change requirements if necessary. You recommend that if a deviation from the contract is detected, the Architecture Board should modify the Architecture Contract to allow the implementation organization the ability to customize the process to meet their local needs. As a result, you then issue a new Request for Architecture Work to implement the modified Architecture Definition.
Answer: D
Explanation:
Q10. Which one of the following best describes Capability-Based Planning?
A. A planning technique that ensures business information is communicated to the right people at the right time
B. A planning technique that ensures the application of business best practices
C. A planning technique that ensures timely solutions
D. A planning technique that focuses on business outcomes
E. A planning technique that identifies services to be shared
Answer: D
Explanation:
Q11. Which of the following does the TOGAF ADM recommend for use in developing the Architecture Vision?
A. Architecture Principles
B. Business Scenarios
C. Interoperability Analysis
D. Migration Planning Techniques
E. Risk Management Techniques
Answer: B
Explanation:
Q12. Which section of the TOGAF template for Architecture Principles highlights the requirements for carrying out the principle?
A. Implications
B. Name
C. Rationale
D. Statement
Answer: A
Explanation:
Q13. Which of the following describes a purpose of an Architecture Compliance review?
A. Identifying relationships between management frameworks
B. Identifying stakeholders and their concerns
C. Identifying the business transformation risks for an architecture project
D. Identifying criteria for procurement activities
E. Identifying work packages for inclusion in the Architecture Roadmap
Answer: D
Reference:http://pubs.opengroup.org/architecture/togaf9-doc/arch/chap48.html#tag_48_03
Q14. Which of the following describes a key objective of the Technology Architecture Phase?
A. To define the solution architecture needed to support the Application Architecture
B. To define technology components into a set of technology platforms
C. To define the Transition Architectures needed to achieve the Target Architecture
D. To develop a migration plan to deliver incremental capabilities
E. To select a set of technology products that will form the basis of a solution architecture
Answer: B
Explanation:
Q15. Which one of the following provides a foundation for making architecture and planning decisions, framing policies, procedures, and standards, and supporting resolution of contradictory situations?
A. Architecture principles
B. Buy lists
C. Procurement policies
D. Requirements
E. Stakeholder concerns
Answer: A
Explanation:
Q16. Scenario
Please read this scenario prior to answering the Question You have been assigned the role of Chief Enterprise Architect within a leading outsourcing services company. The company has over 20,000 outsourcing professionals and works on some of the world's largest outsourcing projects. Outsourcing services include business processes, infrastructure, and service management. The company also provides business consulting services.
With numerous service areas and a large number of diverse engagements in progress at any given time, overall engagement management within the company has become challenging. The company does not want to risk Its outstanding reputation or its international certifications and CMM ratings.
The company has an established an Enterprise Architecture program based on TOGAF 9, sponsored jointly by the Chief Executive Officer and Chief Information Officer. An Architecture Board has been formed comprised of IT staff executives and executives from the major service areas and consulting practice.
The Enterprise Architecture (EA) team has been working with the Strategic Planning team to create a strategic enterprise architecture to address these issues. The EA team has defined a framework and held workshops with key stakeholders to define a set of architecture principles to govern the architecture work. They have completed an Architecture Vision at a strategic level and laid out Architecture Definitions for the four domains. They have set out an ambitious vision of the future of the company over a five-year period. This includes a solution architecture including three distinct transformations.
The CIO has made it clear that prior to the approval of the detailed Implementation and Migration plan, the EA team will need to assess the risks associated with the proposed architecture. He has received concerns from some of the vice presidents across the company that the proposed architecture may be too ambitious and they are not sure it can produce sufficient value to warrant the attendant risks.
Refer to the Scenario
You have been asked to recommend an approach to satisfy these concerns.
Based on TOGAF, which of the following is the best answer?
A. The EA team should gather information about potential solutions from the appropriate sources. Once the Solution Architecture has been assembled, it should be analyzed using a state evolution table to determine the Transition Architectures. A value realization process should then be established to ensure that the concerns raised are addressed.
B. Before preparing the detailed Implementation and Migration plan, the EA team should review and consolidate the gap analysis results from Phases B to D to understand the transformations that are required to achieve the proposed Target Architecture. The EA team should then assess the readiness of the organization to undergo change. Once the Solution Architecture has been assembled, it should be analyzed using a state evolution table to determine the Transition Architectures.
C. The EA team should apply an interoperability analysis to evaluate any potential issues across the Solution Architecture. This should include the development of a matrix showing the interoperability requirements. Once all of the concerns have been resolved, the EA team should finalize the Architecture Roadmap and the Implementation and Migration Plan.
D. The EA team should apply the Business Transformation Readiness Assessment technique. This will allow the risks associated with the transformations to be identified and mitigated for. It will also identify improvement actions to be worked into the Implementation and Migration Plan. The Business Value Assessment technique should then be used to determine the business value and associated risks for the transformation.
Answer: D
Explanation: