Q1. - (Topic 1) When a project manager creates a communication plan, which of the following should be included? (Select TWO). A. Project communication formats B. Financials C. Red, yellow, and green project status D. Escalation path E. Overview of the project F. Risks and issues View AnswerAnswer: A,D Q2. - (Topic 2) Which of the following is the status of an active project with an SPI of 1.1 and…
Q1. - (Topic 3) Which of the following organizational structures is characterized by project team members who work in job-specific departments? A. Functional B. Projectized C. Strong matrix D. Matrix View AnswerAnswer: A Q2. - (Topic 3) A project manager is preparing for a project kick-off meeting in support of a new contract awarded to the organization. The project manager is preparing the agenda for the meeting. The…
Q1. - (Topic 3) A quality management plan should contain which of the following pieces of information? A. Quality budget B. Quality personnel C. Quality metrics D. Quality certification View AnswerAnswer: C Q2. - (Topic 3) Due to organizational turnover, a project is being run by a third project manager. The project manager learns that team members believe the team is meeting too frequently and it is negatively…
Q1. - (Topic 2) A project sponsor has requested significant, additional features to software being developed. Before submitting a change request that will result in changes to the project scope, which of the following activities should the project manager perform? A. Impact analysis B. Budget analysis C. Risk analysis D. Make/buy analysis E. SWOT analysis View AnswerAnswer: A Q2. - (Topic 3) Which of the following include the WBS…
Q1. - (Topic 2) During validation of a business case, which of the following is done to assure that it fits with the company’s overall direction? A. Justification for project B. Identification of stakeholders C. Feasibility analysis D. Alignment to strategic plan View AnswerAnswer: D Q2. - (Topic 2) Opportunities to improve project results are tracked as a part of which of the following aspects of the project? A.…
Q1. - (Topic 1) Which of the following tasks is essential to update a critical production component prior to project delivery? A. Perform post-change testing B. Release project costs C. Receive vendor sign-off D. Initiate change control process View AnswerAnswer: D Q2. - (Topic 2) While creating a project schedule, multiple inputs were considered during estimating, allowing for the identification of best case, worst case, and expected case.…
Q1. - (Topic 2) A project timeline is at risk of not meeting the completion time for developing a smart phone application. In order to meet the date, the code can be pushed out to the testers while getting scanned by the code security software. Development time will be shorter, but there could be a security risk to the application. Which…
Q1. - (Topic 1) One of the project’s team members assigned to work on a specialized set of tasks has suddenly become unavailable and unreachable. Which of the following can the project manager do to ensure the tasks are completed with minimal impact to the project? A. Update the risk matrix and inform the stakeholders B. Reassign the task to a member of…
Q1. - (Topic 3) Which of the following process groups contains quality assurance? A. Initiating B. Executing C. Closing D. Planning View AnswerAnswer: B Q2. - (Topic 1) Which of the following is required to validate a project? A. Problem statement B. Signed project charter C. Key project deliverables D. Alignment with the organization’s strategic goals View AnswerAnswer: D Q3. - (Topic 2) A project involves outsourcing multiple parts of the software application to…
Q1. - (Topic 1) After identifying a change needed in the system, which of the following is the NEXT action the stakeholder should perform? A. Inform the developer B. Inform the resource manager C. Inform the project manager D. Inform the project sponsor View AnswerAnswer: C Q2. - (Topic 3) Approval from which of the following entities is required to make a project charter valid? A. Accounting B. Project sponsor C.…
Q1. - (Topic 2) Which of the following should be updated after a change request has been approved? A. Risk register B. Project charter C. Issues log D. Project scope documents View AnswerAnswer: D Q2. - (Topic 3) The project manager has received an email requesting additional functionality for the application being developed. The resources that are needed to code this functionality are external and the resources’ availability…