Q1. - (Topic 2)
Which of the following should be updated after a change request has been approved?
A. Risk register
B. Project charter
C. Issues log
D. Project scope documents
Answer: D
Q2. - (Topic 3)
The project manager has received an email requesting additional functionality for the application being developed. The resources that are needed to code this functionality are external and the resources’ availability could delay the project. Which of the following items should the project manager produce to document this change? (Select TWO).
A. Scope statement
B. Risk register
C. RACI matrix
D. Change management form
E. Issue log
F. Budget request
Answer: B,D
Q3. - (Topic 2)
The current project manager is developing a report for the stakeholders to approve building a house during the winter months. Which of the following should be done to ensure the stakeholders are aware of any potential outcomes?
A. Identify potential variances
B. Manage costs within budget
C. Monitor work performance
D. Analyze probability and impact
Answer: D
Q4. - (Topic 1)
An active project has an EV of 50,000, an AC of 45,000, and a PV of 50,000. Which of the following represents the current project SPI?
A. -5000
B. .9
C. 1
D. 1.1
Answer: C
Q5. - (Topic 1)
Two project resources have been involved in several heated arguments based on approaches to meet project requirements. The first resource is convinced that the requirement is invalid, whereas the second resource believes that the requirement is valid but should be solved a certain way. As a project manager, which of the following is a suitable conflict resolution approach to attempt to remedy the situation?
A. Attempt ‘smoothing’ and ‘negotiation’ techniques
B. Threaten to report both employees to HR due to bullying
C. Make an executive decision as the project manager
D. Escalate the matter to the project sponsor
Answer: A
Q6. - (Topic 2)
A project manager is working to select a hosting provider prior to the launch of a new web-based application. To reduce the impact of downtime due to catastrophic natural events, the project manager selects a provider with geographically diverse datacenters. This is an example of which of the following risk response strategies?
A. Acceptance
B. Avoidance
C. Mitigation
D. Transfer
Answer: C
Q7. - (Topic 2)
While working on a project, one of the previously recognized threats occurred. In addition to updating the risk register, which of the following documents should be updated?
A. Communication plan
B. WBS
C. Issue log
D. Project schedule
Answer: C
Q8. - (Topic 2)
A project manager just completed a project closure. The project manager completed the following activities: Verify all objectives were completed, all resources were released and all contracts were closed. Which of the following other project closure related activities are missing?
A. Lessons learned, customer signoff, update organizational documents and update historical information
B. Lessons learned, customer signoff, schedule closure and update historical information
C. Project manager signoff, customer signoff, update organizational documents and update historical information
D. Lessons learned, budget signoff, update organizational documents and update financial information
Answer: A
Q9. - (Topic 2)
Which of the following is the main purpose of a work breakdown structure?
A. To decompose the list of deliverables
B. To identify key stakeholders and their influence
C. To assign resources to activities
D. To determine total project duration
Answer: A
Q10. - (Topic 2)
Which of the following would be the MOST important inputs for the development of a project schedule? (Select TWO).
A. Activity durations
B. Procurement plan
C. Project assumptions
D. Task dependencies
E. Cost estimates
Answer: A,D
Q11. - (Topic 3)
The project manager informs the team that the client has approved a change in the direction of the project. Which of the following tasks should the project manager perform NEXT?
A. Update cost and schedule baselines
B. Schedule meetings based on the project schedule
C. Review the communications plan and follow the steps
D. Establish project quality by using the quality management metrics
Answer: A
Q12. - (Topic 3)
The project manager has completed the first round of identifying and documenting the project risks and response plans. Which of the following has been used?
A. Risk matrix
B. Risk assessment plan
C. Risk register
D. Risk response plan
Answer: C
Q13. - (Topic 1)
A project manager will initially baseline a project when:
A. change requests are approved.
B. stakeholders request project initiation.
C. creating a project charter.
D. tasks and estimates have been identified.
Answer: D
Q14. - (Topic 2)
Which of the following items would be found in a project scope statement?
A. Key performance indicators
B. High-level cost estimates
C. Acceptance criteria
D. Bottom-up estimates
Answer: A
Q15. - (Topic 1)
The scope document is created based on the direct input of which of the following documents?
A. Cost management plan
B. Organizational strategic goals
C. Project charter
D. Work breakdown structure
Answer: C
Q16. - (Topic 3)
A request for a change to the project is received. The project manager reviews the request, which appears to have no impact to the cost of the project or the schedule. Which of the following would be the NEXT step the project manager should take?
A. Review the requested change with the project sponsor
B. Discuss the impact of the change with the team
C. Quickly implement the change and notify the team
D. Record the requested change on a change request form
Answer: D