Master the content and be ready for exam day success quickly with this . We guarantee it!We make it a reality and give you real in our CompTIA PK0-004 braindumps. Latest 100% VALID at below page. You can use our CompTIA PK0-004 braindumps and pass your exam.
Free PK0-004 Demo Online For Microsoft Certifitcation:
NEW QUESTION 1
Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?
Answer: D
Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 326
NEW QUESTION 2
Two team members have concluded that documentation is not required due to the size of the current project. The project manager has encouraged them to align strictly within the process.
Which of the following conflict resolution techniques has the project manager utilized?
Answer: B
Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 200
NEW QUESTION 3
An authorized change to a construction project was implemented. During the modification, the team identified ADefect in which the change caused the building power output to be outside the KPPs.
Which of the following actions should the project manager take?
Answer: B
Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 294
NEW QUESTION 4
A quality auditor finds suspicious code during a software test. For which of the following could this be a trigger?
Answer: A
NEW QUESTION 5
A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services.
Which of the following documents will the company MOST likely release FIRST?
Answer: B
Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 300
NEW QUESTION 6
Three IT companies have agreed to summarize their efforts as a common organization to generate new businesses in the IT cloud computing industry. Which of the following is the type of organizational change described?
Answer: C
NEW QUESTION 7
A risk with a high probability and medium consequence to a project has been identified. In response, the project manager has purchased an insurance plan with the intent to provide additional funds if the risk is realized. There is no risk to the schedule or scope. Which of the following types of risk strategies is this an example of?
Answer: B
Explanation: “Transfer: Moving the liability for the risk to a third party by purchasing insurance, performance bonds, and so on”
Excerpt From: Kim Heldman. “CompTIA Project+ Study Guide.” iBooks.
NEW QUESTION 8
Which of the following describes KPIs?
Answer: C
NEW QUESTION 9
A project team member highlights to the project manager that expensive licensing for critical software in use across the project may expire before the completion project.
Which of the following would the project manager MOST likely do?
Answer: A
NEW QUESTION 10
The project sponsor has cut the resources required for project completion. The project manager cannot complete the project without additional resources.
Which of the following should the project manager do to obtain the resources?
Answer: A
NEW QUESTION 11
A project manager was directed to complete a project sooner than previously planned. Which of the following is the MOST cost-effective step to take to ensure the project’s success?
Answer: D
Explanation: References: https://books.google.co.za/books?id=evR0gPFBHJ4C&pg=PA128&lpg=PA128&dq=complete+a+project+soon
NEW QUESTION 12
Which of the following documents should be used to provide high-level reporting to key stakeholders?
Answer: A
Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 325
NEW QUESTION 13
A project’s key stakeholders have requested significant changes that will affect the scope. To adjust the project scope, which of the following need to be changed? (Choose two.)
Answer: BE
Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 133 https://books.google.co.za/books?id=evR0gPFBHJ4C&pg=PA128&lpg=PA128&dq=complete+a+project+soon
NEW QUESTION 14
When a risk event occurs, which of the following documents is BEST suited for recording and tracking new items corresponding to the risk?
Answer: D
NEW QUESTION 15
After identifying all known tasks, the project manager has started to sequence and set durations.
Which of the following describes how the project manager should BEST determine the initial sequence and durations?
Answer: A
NEW QUESTION 16
A vendor has accepted a proposed project from a customer.
Which of the following is MOST likely to be the first document created by the project manager?
Answer: C
Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 299
NEW QUESTION 17
A project has fallen behind schedule for no obvious reason, so the PM has gathered the team to brainstorm. Which of the following should the PM do NEXT?
Answer: B
NEW QUESTION 18
A company has updated the method it uses to initiate projects. The company requires RFPs from three vendors, and low and high bids must be rejected to determine the selected vendor.
Which of the following terms describe this requirement?
Answer: A
Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 297
Thanks for reading the newest PK0-004 exam dumps! We recommend you to try the PREMIUM Certleader PK0-004 dumps in VCE and PDF here: https://www.certleader.com/PK0-004-dumps.html (246 Q&As Dumps)