Want to know Examcollection PMI-001 Exam practice test features? Want to lear more about PMI Project Management Professional certification experience? Study Verified PMI PMI-001 answers to Most recent PMI-001 questions at Examcollection. Gat a success with an absolute guarantee to pass PMI PMI-001 (Project Management Professional) test on your first attempt.
Online PMI PMI-001 free dumps demo Below:
NEW QUESTION 1
What is the critical chain method?
Answer: B
NEW QUESTION 2
An output of the Validate Scope process is:
Answer: D
NEW QUESTION 3
What does a CPI value greater than 1.0 indicate?
Answer: B
NEW QUESTION 4
The scope management plan and scope baseline are contained in:
Answer: D
NEW QUESTION 5
The application of knowledge, skills, tools, and techniques to project activities to meet project requirements describes management of which of the following?
Answer: A
NEW QUESTION 6
Which of the following is an input to Develop Human Resource Plan?
Answer: D
NEW QUESTION 7
Which of the following is an example of contract administration?
Answer: B
NEW QUESTION 8
A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?
Answer: D
NEW QUESTION 9
Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?
Answer: B
NEW QUESTION 10
Within project integration management, the statement of work (SOW) references which aspects of the project?
Answer: A
NEW QUESTION 11
An output of the Develop Project Team process is:
Answer: B
NEW QUESTION 12
Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?
Answer: A
NEW QUESTION 13
Which Process Group includes the Manage Stakeholder Engagement process?
Answer: C
NEW QUESTION 14
Most experienced project managers know that:
Answer: B
NEW QUESTION 15
The initial development of a Project Scope Management plan uses which technique?
Answer: C
NEW QUESTION 16
Which process involves developing an approximation of the monetary resources needed to complete project activities?
Answer: A
NEW QUESTION 17
Stakeholder management strategy is an output of:
Answer: D
NEW QUESTION 18
Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?
Answer: C
NEW QUESTION 19
What type of reward can hurt team cohesiveness?
Answer: B
NEW QUESTION 20
Which of the following includes how requirements activities will be planned, tracked, and reported?
Answer: C
NEW QUESTION 21
Risk responses reflect an organization's perceived balance between:
Answer: A
NEW QUESTION 22
An output of the Perform Integrated Change Control process is:
Answer: C
NEW QUESTION 23
Which of the following is an output of the Perform Integrated Change Control process?
Answer: A
NEW QUESTION 24
In which Knowledge Area is the project charter developed?
Answer: D
NEW QUESTION 25
Which is an example of Administer Procurements?
Answer: B
NEW QUESTION 26
Which process develops options and actions to enhance opportunities and reduce threats to project objectives?
Answer: D
NEW QUESTION 27
Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?
Answer: B
NEW QUESTION 28
A method to manage stakeholder expectations in the scope statement is to clearly:
Answer: C
NEW QUESTION 29
......
P.S. Easily pass PMI-001 Exam with 919 Q&As Certshared Dumps & pdf Version, Welcome to Download the Newest Certshared PMI-001 Dumps: https://www.certshared.com/exam/PMI-001/ (919 New Questions)