we provide High quality PMI PMI-ACP download which are the best for clearing PMI-ACP test, and to get certified by PMI PMI Agile Certified Practitioner (PMI-ACP)®. The PMI-ACP Questions & Answers covers all the knowledge points of the real PMI-ACP exam. Crack your PMI PMI-ACP Exam with latest dumps, guaranteed!
Online PMI-ACP free questions and answers of New Version:
NEW QUESTION 1
Project managers use velocity to determine:
- A. If the team is committing to an appropriate amount of work for the iteration.
- B. How much work each team member is capable of completing during an iteration.
- C. How much work teams that are similar in size are capable of completing during an iteration.
- D. If the Product Owner is prioritizing work appropriately in preparation for iteration planning.
Answer: A
NEW QUESTION 2
A story point is the:
- A. Relative measure of the size of a user story.
- B. Duration it takes to complete a user story.
- C. Priority of the user story in the backlog.
- D. Business value of the user story.
Answer: A
NEW QUESTION 3
The ScrumMaster and the Product Owner disagree on the value of a Product Backlog item. In order to resolve the disagreement, the first step the ScrumMaster should take is to ask:
- A. The Product Owner to clarify the requirement.
- B. The business owner to resolve the problem.
- C. The business analyst to research the product value.
- D. Another project manager how to resolve the problem.
Answer: A
NEW QUESTION 4
The most appropriate model for a geographically distributed project team is one in which the team is distributed across:
- A. relatively few locations, with each location team comprised of a complete development group developing decoupled subsystems.
- B. locations in the same time zone, working on the same systems while leveraging rich communication channels.
- C. relatively few locations, and tasks are divided along functional lines with design in one location, coding in another, and testing in another.
- D. many locations, with relatively few people at each location developing and testing decoupled subsystems.
Answer: A
NEW QUESTION 5
Which of the following is a list of valid Agile project planning practices?
- A. Release planning, Iteration planning, and Estimation
- B. Estimation, Spike Solutions, and Iteration planning
- C. Iteration planning, Continuous Integration, and Estimation
- D. Vision, Release planning, and Performance Optimization
Answer: A
NEW QUESTION 6
A high-performance Agile team:
- A. is fully committed to team success yet respects the prescribed roles and titles of team members.
- B. owns its decisions and commitments and is motivated to succeed at any cost.
- C. is self-organizing, empowered to make decisions, and consensus-driven, with constructive disagreement.
- D. produces a high volume of business value through intensive collaboration and avoidance of conflict.
Answer: C
NEW QUESTION 7
When are acceptance tests typically written for a user story?
- A. After coding the story, but before user acceptance testing begins
- B. After writing the story, but before coding begins
- C. At the start of Product Backlog prioritization planning
- D. After estimating the Product Backlog, but before Sprint planning begins
Answer: C
NEW QUESTION 8
Information transmission is greatest amongst team members who are working on:
- A. Individual tasks in the same work area.
- B. The same task through pair programming.
- C. The same group of tasks individually.
- D. Different tasks on the same project.
Answer: B
NEW QUESTION 9
When developing user stories, user expectations are best captured in what form?
- A. Acceptance tests
- B. Entrance criteria
- C. Done criteria
- D. Go and no-go limits
Answer: A
NEW QUESTION 10
Which of the seven principles of software development is best intended to solve the problem of inventories causing hidden errors in the process?
- A. Fast-Flexible-Flow
- B. Optimize the Whole
- C. Deliver Early and Often
- D. Eliminate Waste
Answer: D
NEW QUESTION 11
Which of the following drivers is the most important factor in determining the order in which stories will be developed?
- A. Relative cost
- B. Customer value
- C. Development effort
- D. Dependencies
Answer: B
NEW QUESTION 12
What do project reports show during the Sprint review meeting?
- A. Estimates compared to the baseline
- B. Actual results to the plan
- C. Return on investment (ROI)
- D. Earned value measurement (EVM)
Answer: C
NEW QUESTION 13
Which of the following best represents both a principle of the Agile manifesto and a Lean method of simplicity?
- A. Maximizing the amount of work not done
- B. Delivering early and continuously
- C. Welcoming changing requirements
- D. Deciding at the last responsible moment
Answer: A
NEW QUESTION 14
Acceptance tests of user stories are specified by the:
- A. Customer at the start of the iteration.
- B. Customer as late as possible during the iteration.
- C. Tester after the team has finished the coding.
- D. Development team at the start of the iteration.
Answer: A
NEW QUESTION 15
A development team has finished identifying the tasks they will be accountable for during the next sprint. Which of the following tools best provides transparency into the progress throughout the sprint?
- A. Burndown chart
- B. Gantt chart
- C. Hours expended chart
- D. Management baseline chart
Answer: A
NEW QUESTION 16
Which of the following would be most likely to assist when a customer has difficulty prioritizing stories?
- A. Split the stories into smaller ones to allow the customer to choose the pieces that they want.
- B. Have the team provide guidance into where their priorities lie to the customer.
- C. Provide additional technical details to give the customer insight into technical challenges.
- D. Have the team rewrite the stories with additional details to clarify requirements.
Answer: A