PMP Premium Bundle

PMP Premium Bundle

Project Management Professional Certification Exam

4.5 
(47445 ratings)
0 QuestionsPractice Tests
0 PDFPrint version
September 29, 2024Last update

PMP PMP Free Practice Questions

It is more faster and easier to pass the by using . Immediate access to the and find the same core area with professionally verified answers, then PASS your exam with a high score now.

Also have PMP free dumps questions for you:

NEW QUESTION 1
The primary benefit of the Plan Schedule Management process is that it:

  • A. provides guidance to identify time or schedule challenges within the project.
  • B. tightly links processes to create a seamless project schedule.
  • C. guides how the project schedule will be managed throughout the project.
  • D. creates an overview of all activities broken down into manageable subsections.

Answer: C

NEW QUESTION 2
A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:

  • A. mitigate
  • B. accept
  • C. transfer
  • D. avoid

Answer: C

NEW QUESTION 3
Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:

  • A. Available organizational assets
  • B. Project staff assignments
  • C. Interpersonal skills
  • D. Enterprise environmental factors

Answer: A

NEW QUESTION 4
Which of the following is TRUE about most project life cycles?

  • A. Staffing level is highest at the start.
  • B. The stakeholders' influence is highest at the start.
  • C. The level of uncertainty is lowest at the start.
  • D. The cost of changes is highest at the start.

Answer: B

NEW QUESTION 5
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?

  • A. Product scope description
  • B. Procurement statement of work
  • C. Project schedule
  • D. Work breakdown structure (WBS)

Answer: B

NEW QUESTION 6
Which of the following methods is a project selection technique?

  • A. Flowcharting
  • B. Earned value
  • C. Cost-benefit analysis
  • D. Pareto analysis

Answer: C

NEW QUESTION 7
In which process is a project manager identified and given the authority to apply resources to project activities?

  • A. Acquire Project Team
  • B. Develop Project Management Plan
  • C. Manage Project Execution
  • D. Develop Project Charter

Answer: D

NEW QUESTION 8
Which of the following is a component of three-point estimates?

  • A. Probabilistic
  • B. Most likely
  • C. Expected
  • D. Anticipated

Answer: B

NEW QUESTION 9
Which of the following is a strategy to deal with positive risks or opportunities?

  • A. Mitigate
  • B. Transfer
  • C. Exploit
  • D. Avoid

Answer: C

NEW QUESTION 10
Ensuring that both parties meet contractual obligations and that their own legal rights are protected is a function of:

  • A. Conduct Procurements.
  • B. Close Procurements.
  • C. Administer Procurements,
  • D. Plan Procurements.

Answer: C

NEW QUESTION 11
Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?

  • A. Variance Analysis
  • B. Define Scope
  • C. Verify Scope
  • D. Control Scope

Answer: D

NEW QUESTION 12
Which tool or technique of Plan Quality involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance?

  • A. Histogram
  • B. Quality audits
  • C. Benchmarking
  • D. Performance measurement analysis

Answer: C

NEW QUESTION 13
Verification of project deliverables occurs during which process?

  • A. Develop preliminary project scope statement
  • B. Close Project or Phase
  • C. Develop project charter
  • D. Create WBS

Answer: B

NEW QUESTION 14
Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:

  • A. Enterprise environmental factors
  • B. Work performance reports
  • C. Organizational process assets
  • D. Context diagrams

Answer: A

NEW QUESTION 15
Which is an example of Administer Procurements?

  • A. Negotiating the contract
  • B. Authorizing contractor work
  • C. Developing the statement of work
  • D. Establishing evaluation criteria

Answer: B

NEW QUESTION 16
Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?

  • A. Cost variance (CV)
  • B. Cost performance index (CPI)
  • C. Budget at completion (BAC)
  • D. Variance at completion (VAC)

Answer: B

NEW QUESTION 17
The Human Resource Management processes are:

  • A. Develop Human Resource Plan, Acquire Project Team, Develop Project Team, and Manage Project Team.
  • B. Acquire Project Team, Manage Project Team, Manage Stakeholder Expectations, and Develop Project Team.
  • C. Acquire Project Team, Develop Human Resource Plan, Conflict Management, and Manage Project Team.
  • D. Develop Project Team, Manage Project Team, Estimate Activity Resources, and Acquire Project Team.

Answer: A

P.S. Easily pass PMP Exam with 918 Q&As Certshared Dumps & pdf Version, Welcome to Download the Newest Certshared PMP Dumps: https://www.certshared.com/exam/PMP/ (918 New Questions)


START PMP EXAM