Our pass rate is high to 98.9% and the similarity percentage between our PMP study guide and real exam is 90% based on our seven-year educating experience. Do you want achievements in the PMP PMP exam in just one try? I am currently studying for the PMP PMP exam. Latest PMP PMP Test exam practice questions and answers, Try PMP PMP Brain Dumps First.

Free PMP Demo Online For PMP Certifitcation:

NEW QUESTION 1

As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total project cost. You should calculate the forecast using which of the following methods?

  • A. BAC
  • B. EAC
  • C. ETC
  • D. WBS

Answer: B

NEW QUESTION 2

Which can be used to determine whether a process is stable or has predictable performance?

  • A. Matrix diagram
  • B. Histogram
  • C. Control chart
  • D. Flowchart

Answer: C

NEW QUESTION 3

Which of the following includes how requirements activities will be planned, tracked, and reported?

  • A. Configuration management plan
  • B. Scope baseline
  • C. Requirements management plan
  • D. Schedule baseline

Answer: C

NEW QUESTION 4

Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering?

  • A. The Delphi technique
  • B. Nominal group technique
  • C. Affinity diagram
  • D. Brainstorming

Answer: A

NEW QUESTION 5

Cost baseline is an output of which of the following processes?

  • A. Control Costs
  • B. Determine Budget
  • C. Estimate Costs
  • D. Estimate Activity Resources

Answer: B

NEW QUESTION 6

Plan-do-check-act is also known as:

  • A. prevention over inspection.
  • B. statistical sampling.
  • C. management responsibility,
  • D. continuous improvement.

Answer: D

NEW QUESTION 7

The individual or group that provides resources and support for a project and is accountable for success is the:

  • A. sponsor
  • B. customer
  • C. business partners
  • D. functional managers

Answer: A

NEW QUESTION 8

Issue change requests and adapt approved changes into the project’s scope, plans, and environment is an activity included in which of the following project management processes?

  • A. Direct and Manage Project Execution
  • B. Monitor and Control Project Work
  • C. Perform Integrated Change Control
  • D. Monitor and Control Risks

Answer: A

NEW QUESTION 9

An output of the Develop Project Team process is:

  • A. change requests
  • B. team performance assessments
  • C. project staff assignments
  • D. project documents updates

Answer: B

NEW QUESTION 10

The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?

  • A. Timing
  • B. Methodology
  • C. Risk categories
  • D. Budgeting

Answer: A

NEW QUESTION 11

Who selects the appropriate processes for a project?

  • A. Project stakeholders
  • B. Project sponsor and project stakeholder
  • C. Project manager and project team
  • D. Project manager and project sponsor

Answer: C

NEW QUESTION 12

The links between the processes in the Process Groups are often:

  • A. Intuitive
  • B. Iterative
  • C. Measured
  • D. Monitored

Answer: B

NEW QUESTION 13

The following chart contains information about the tasks in a project.
PMP dumps exhibit
Based on the chart, what is the cost performance index (CPI) for Task 2?

  • A. 0.8
  • B. 1
  • C. 1.25
  • D. 1.8

Answer: C

NEW QUESTION 14

Which process develops options and actions to enhance opportunities and reduce threats to project objectives?

  • A. Identify Risks
  • B. Control Risks
  • C. Plan Risk Management
  • D. Plan Risk Responses

Answer: D

NEW QUESTION 15

Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?

  • A. Interrelationship digraphs
  • B. Tree diagram
  • C. Affinity diagram
  • D. Network diagram

Answer: B

NEW QUESTION 16

Testing falls into which of the following categories of cost of quality?

  • A. Internal failure costs
  • B. Prevention costs
  • C. Appraisal costs
  • D. External failure costs

Answer: C

NEW QUESTION 17

Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?

  • A. Control Schedule
  • B. Define Activities
  • C. Develop Schedule
  • D. Estimate Activity Resources

Answer: D

NEW QUESTION 18

Which tool and technique is used in Conduct Procurements?

  • A. Teaming agreements
  • B. Expert judgment
  • C. Bidder conferences
  • D. Contract types

Answer: C

NEW QUESTION 19

Which is an enterprise environmental factor?

  • A. Marketplace conditions
  • B. Policies and procedures
  • C. Project files from previous projects
  • D. Lessons learned from previous projects

Answer: A

NEW QUESTION 20

The project manager at an organization has just realized that some of the engineering staff has been allocated to project Y and will not be available to finish task X. The project manager has also discovered that at the current pace, it will not be possible to complete the project on time. Due to cost constraints, hiring more work force is not a viable option. Which tools are at the manager's disposal?

  • A. Resource leveling and fast tracking
  • B. Fast tracking and crashing
  • C. Crashing and applying leads and lags
  • D. Scheduling tools and applying leads and lags

Answer: A

NEW QUESTION 21

Projects can intersect with an organization’s operations at various points during the product life cycle such as:

  • A. When there is an operations shutdown (i.
  • B. a strike).
  • C. When developing new products, upgrading products, or expanding outputs.
  • D. When a project transitions from a temporary to a permanent status.
  • E. When the project manager is promoted to operations manager.

Answer: B

NEW QUESTION 22

Which technique is commonly used for the Quantitative Risk Analysis activity?

  • A. Brainstorming
  • B. Strategies for Opportunities
  • C. Decision Tree Analysis
  • D. Risk Data Quality Assessment

Answer: C

NEW QUESTION 23

A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:

  • A. Benchmarking.
  • B. Context diagrams.
  • C. Brainstorming.
  • D. Prototyping.

Answer: D

NEW QUESTION 24

In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?

  • A. Start-to-start (SS)
  • B. Start-to-finish (SF)
  • C. Rnish-to-finish (FF)
  • D. Finish-to-start (FS)

Answer: D