PRINCE2-Foundation Premium Bundle

PRINCE2-Foundation Premium Bundle

PRINCE2 Foundation exam Certification Exam

4.5 
(19785 ratings)
0 QuestionsPractice Tests
0 PDFPrint version
September 29, 2024Last update

PRINCE2-Exams PRINCE2-Foundation Free Practice Questions

Q1. - (Topic 1) 

Which should be funded from a change budget? 

A. The Starting up a Project process 

B. A fallback plan 

C. An agreed change to the scope of a project 

D. A change to a plan, within allocated tolerances, due to poor estimating 

Answer:

Q2. - (Topic 2) 

Which statement applies to Stage Plans? 

A. Always have the same duration as the Project Plan 

B. Are produced at the same time as the Project Initiation Documentation 

C. Assist the Project Manager in the day-to-day running and control of the project 

D. Provide a baseline against which the Project Board monitor overall progress 

Answer:

Q3. - (Topic 1) 

Which is a typical core activity within configuration management? 

A. Quality assurance 

B. Risk management 

C. Verification and audit 

D. Progress reporting 

Answer:

Q4. - (Topic 1) 

Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties. 

A. Stage Plan 

B. Communication Management Strategy 

C. Follow-on action recommendations 

D. Quality Management Strategy 

Answer:

Q5. - (Topic 2) 

Identify the missing word in the following sentence. The risk response type [ ? ] can be 

used to respond to a threat and an opportunity. 

A. Avoid 

B. Reduce 

C. Share 

D. Transfer 

Answer:

Q6. - (Topic 1) 

Which is the purpose of the Change theme? 

A. Prevent change to baselined products 

B. Identify, assess and control any potential and approved changes to baselined products 

C. Establish mechanisms to monitor and compare actual achievements against those planned 

D. Assess and control uncertainty 

Answer:

Q7. - (Topic 2) 

During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin? 

A. End Stage Report 

B. Team Plan 

C. Work Package 

D. Project Plan 

Answer:

Q8. - (Topic 1) 

Which is NOT a purpose of the Initiating a Project process? 

A. Enable a Project Board decision about the commitment of resources to a project 

B. Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved 

C. Establish solid foundations for a project 

D. Enable the Project Board to decide whether it is worthwhile to initiate a project 

Answer:

Q9. - (Topic 2) 

Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable? 

A. Risk category 

B. Risk description 

C. Risk response 

D. Risk status 

Answer:

Q10. - (Topic 2) 

Which is shown in a product breakdown structure? 

A. Management stages, major products and control points 

B. In which order the products should be created 

C. The major products that are to be developed in a plan 

D. What resources are required to develop the products 

Answer:

Q11. - (Topic 1) 

Which is a purpose of the Directing a Project process? 

A. Create and authorize the project mandate 

B. Ensure that work on products allocated to the team is authorized and agreed 

C. Control the day-to-day running of the project 

D. Delegate day-to-day management of the project to the Project Manager 

Answer:

Q12. - (Topic 1) 

Which should be funded by a change budget? 

A. Increase in agreed scope 

B. Initiation stage 

C. Change Authority 

D. Handover activities 

Answer:

Q13. - (Topic 2) 

What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance? 

A. Configuration Item Record 

B. Quality Register 

C. Highlight Report 

D. Checkpoint Report 

Answer:

Q14. - (Topic 1) 

Which of the following statements about the Project Initiation Documentation are true? 

1. 

The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project. 

2. 

The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project. 

A. Only 1 is true 

B. Only 2 is true 

C. Both 1 and 2 are true 

D. Neither 1 or 2 are true 

Answer:

Q15. - (Topic 1) 

Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions? 

A. Project Brief 

B. Project Initiation Documentation 

C. Project mandate 

D. Benefits Review Plan 

Answer:

Q16. - (Topic 2) 

Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities. 

A. change budget 

B. project budget 

C. project's cost tolerance 

D. project's risk tolerance 

Answer:

Q17. - (Topic 2) 

Which statement about the quality review technique is FALSE? 

A. It enables a check to be made on a product's fitness for purpose 

B. It defines the quality responsibilities of the project team 

C. It supports the management of future changes by providing a baseline for a product 

D. It is used to gain wider acceptance of a product by involving key interested parties 

Answer:

START PRINCE2-Foundation EXAM