Q1. - (Topic 2)
Why is a Project Brief produced?
A. To act as a trigger for the Starting up a Project process
B. To record the strategies and management controls to be used by a project
C. To provide a full and firm foundation for the initiation of a project
D. To be used by the Project Board as a basis for reviewing the progress of a project
Answer: C
Q2. - (Topic 1)
Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.
A. a corporate
B. a temporary
C. an external
D. a technical
Answer: B
Q3. - (Topic 2)
Which is a true statement about acceptance criteria?
A. Acceptance criteria are used to produce the customer's quality expectations
B. Acceptance criteria are less specific and precise than customer's quality expectations
C. Once agreed, acceptance criteria CANNOT be changed
D. Acceptance criteria should be agreed between the customer and the supplier
Answer: D
Q4. - (Topic 2)
Which is a recommended quality review team role?
A. Project Manager
B. Assurance
C. Chair
D. Producer
Answer: C
Q5. - (Topic 2)
Which statement defines a risk?
A. A certain event occurring in the future that will have a negative impact on the project's objectives
B. An event that has already occurred that the Project Manager must deal with immediately
C. An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives
D. An uncertain event, or set of events that, should it or they occur, will be automatically escalated to the Project Board for a response
Answer: C
Q6. - (Topic 2)
Why is it crucial that the Project Product Description clearly defines acceptance methods?
A. Enables Project Assurance to authorize quality activities
B. Defines how all project products will be reviewed and approved
C. Defines how it will be proven that the completed project product meets the customer's expectations
D. Provides confirmation that all project products have met their quality criteria
Answer: C
Q7. - (Topic 2)
Which should be provided by corporate or programme management before the Starting up a Project process commences?
A. A Project Brief
B. Sufficient information to identify the prospective Executive
C. The Project Initiation Documentation
D. Authority to initiate a project
Answer: B
Q8. - (Topic 1)
When should the Project Board refer to corporate or programme management for a decision?
A. The stage requires resources
B. It is forecast that project level tolerance will be exceeded
C. The Senior Supplier or Senior User needs to be changed
D. Any request for change needs to be approved
Answer: B
Q9. - (Topic 2)
Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.
A. controls
B. products
C. project management team
D. stages
Answer: B
Q10. - (Topic 2)
Which is a purpose of the Risk theme?
A. Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
B. Establish a cost-effective procedure to identify, assess and control uncertainty
C. Establish mechanisms to control any unacceptable deviations from plan
D. Establish mechanisms to manage risks at the corporate or programme level of an organization
Answer: B
Q11. - (Topic 2)
What is described as an organization's unique attitude towards risk taking
A. Risk appetite
B. Risk management
C. Risk evaluation
D. Risk tolerance
Answer: A
97. - (Topic 2)
Identify the missing words in the following sentence. The role of [ ? ] is responsible for carrying out a risk response action to respond to a particular risk.
A. Project Assurance
B. Project Support
C. the risk actionee
D. the risk owner
Q12. - (Topic 2)
Which is NOT considered when defining risk tolerance?
A. A Project Board's attitude towards risk taking
B. The allocated risk budget
C. An organization's risk appetite
D. The amount of risk a Project Board considers acceptable
Answer: B
Q13. - (Topic 1)
Which is NOT a purpose of a Benefits Review Plan?
A. Define the period over which the cost-benefit analysis will be based
B. Describe how to measure the performance of the project's products in operational use
C. Define the scope, timing and ownership of the benefit reviews required
D. Describe how to measure and confirm any benefits that are to be realised after the project is closed
Answer: A
Q14. - (Topic 1)
Which two roles are linked by the Managing Product Delivery process?
A. Corporate or programme management and Project Board
B. Project Board and Project Manager
C. Project Manager and Team Manager
D. Team Manager and external supplier
Answer: C
Q15. - (Topic 1)
Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?
A. Capture
B. Examine
C. Propose
D. Decide
Answer: C
Q16. - (Topic 2)
Which is a purpose of a Project Brief?
A. Enable the assembly of the project mandate
B. Describe the reporting requirements of the various layers of management involved with the project
C. Describe how changes to products will be controlled
D. Provide a solid basis for the initiation of the project
Answer: D
Q17. - (Topic 2)
Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ? ] the project's plans.
A. define a coding system to provide a unique identifier for the products within
B. summarize the results of the quality activities performed on
C. provide a framework to design, develop and maintain
D. define the project benefits to be achieved by each of
Answer: C